Village of Sayward – Water Treatment Plant
Design-Build modular Dissolved Air Flotation (DAF) potable water treatment plant for the Village of Sayward. Size and capacity to treat and convey water sourced from Newcastle Creek to maximum daily demand of the Village of Sayward. Plant includes disinfection dosing system, alarms and all associated piping and electrical systems required to meet the requirements of the Vancouver Health Authority potable water requirements. Work includes the construction of a 1500m3 epoxy coated bolted steel tank raw water reservoir, settling pond, site grading and tie-into existing intake and water distribution.
Client Company:
Village of Sayward
Location:
Sayward, BC
Completion Date:
March 2019